Design Project Management
Road Construction / CEI

Vanderbilt Beach Road Extension Phase 2 (16th St. NE to Everglades Blvd.)

(Project Manager: Bee Thao, P.E.)

VBRX II location map smallThis approximate two-mile new roadway extension will continue Vanderbilt Beach Road to Everglades Blvd. (Extension Project Phase I is currently being constructed up to 16th St. NE). Phase II will be initially constructed as an undivided two-lane roadway with shoulders, curb and gutters, and a paved multi-use pathway The initial improvement is being designed within a four-lane divided roadway right-of-way footprint which will accommodate future projected traffic volumes. A 30 Percent Design Plans Public Information Meeting will be held on Wednesday, June 5, at the UF/IFAS Extension Office, Multipurpose Room, 14700 Immokalee Road, Naples, FL 34120. The meeting will be an open house format from 5 p.m. to 7 p.m. There will not be a formal presentation. The consultant has prepared a handout for this project.

 

Airport Road Widening Project (from Vanderbilt Beach Road to Immokalee Road)

(Project Manager: Bee Thao, P.E.)

Airport Road WideningThe project will widen the Airport Road corridor into a six-lane divided urban arterial roadway by adding an additional travel lane in each direction and on-street bicycle facilities. Travel lanes are being planned as 11-feet wide. In addition, plans call for a 22-foot raised median, curb and gutter and reconstruction of sidewalks along both sides of the roadway, a closed drainage system, street lighting and minor traffic signal improvements. Design for the roadway improvements is anticipated to be completed by Spring 2025; construction may begin as early as summer of 2026.

A public information meeting on Tuesday, Dec. 5, 2023 informed the residents about the 30 percent design stage. The display boards showed the 30% planned layout of the roadway and the typical sections. There was also a handout which includes a comment sheet.

 

Vanderbilt Drive Sidewalk Project (from Vanderbilt Beach Rd to 109th Ave N)

(Project Manager: Michael Tisch)

Vanderbilt Drive SidewalksThis project involves constructing a 5-foot concrete sidewalk on the east side of Vanderbilt Drive.  A pedestrian crosswalk and Rapid Rectangular Flashing Beacon (RRFB) will also be added to allow pedestrians and bicyclists to cross to the west side of Vanderbilt Drive where the sidewalk continues from 109th Ave. N. to 111th Ave. N. Construction could start in late summer/early fall of 2024.

An open house style public information meeting was held on Thursday, Jan. 18. The design team presented the project layout and typical section as well as an overview of the current Naples Park area projects. Comments were received during the meeting as well as via email/mail afterwards. 

 

16th Street NE Bridge Project (from Golden Gate Blvd to Randall Blvd)

(Project Manager: Dennis McCoy, P.E.)

16th Street North East Project DiagramThe project is located along 16th Street NE between Golden Gate Boulevard and Randall Boulevard. The project will help improve safety and accommodate emergency response times within the Golden Gate Estates area.

The project includes:

  • Two 11-foot travel lanes with 6-foot shoulders (4-foot paved plus 2-foot unpaved) along the entire length of the project
  • 6-foot concrete sidewalk on the west side of the roadway
  • New bridge over Golden Gate Main Canal with two 12-foot travel lanes (one in each direction), a 6-foot shoulder on the west side and 12-foot shoulder on the east side.
  • New traffic signal at intersection of 16th Street NE and Randall Boulevard

A public information meeting on the project’s 60 percent design plans stage was held on Thursday, June 15, 2023. A handout has been created with all relevant information as well as conceptual maps (2 pages) and a typical section display.

 

Vanderbilt Beach Road Widening Project from East of US 41 to East of Goodlette-Frank Road

(Project Manager: Dennis McCoy, P.E.)

Vanderbilt Beach Road US41 to Airport Location MapThis road widening project will expand Vanderbilt Beach Road from four to six lanes and extend approximately 1.8 miles from just east of US 41 to approximately the intersection of Vanderbilt Beach Road and Fontana Del Sol Way.

Much of the lane expansion will occur in the existing median. The project will include: improved roadway intersections at Strada Place and Goodlette-Frank Road; maintaining existing sidewalks and providing bike lanes; improved drainage throughout the project area.

Collier County held a public information meeting for the 60% Design Plans on Tuesday, March 30, 2021. Click here for a copy of the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information.

The meeting displays are available here:

The final design plans are currently under review and construction is slated to begin in fall of 2024.

 

Collier Boulevard Widening Phase III

 (Project Manager: Bee Thao, P.E.)

Collier Blvd Phase IIIThe project is located along Collier Boulevard between City Gate Boulevard North and Green Boulevard. The project involves widening Collier Boulevard from four- to six-lanes within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six-lane roadway. This project includes widening within the median and along the west side of Collier Boulevard and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot-wide shared-use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW.

The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed improvements. The new replacement bridge will be at 27th Avenue SW.

A Public Information Meeting at the 60% design stage was held on April 6, 2022. The following displays were provided:

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer